Elevated Expressway 50pc completed


Published : 23 Nov 2019 09:27 PM | Updated : 07 Sep 2020 06:35 PM

The works of the Dhaka Elevated Expressway construction achieved at least 50 percent progress so far. As the financial complexity is over, now the construction work of expressway is being conducted at a faster pace.
With the new scheduled time, the authority concerned is now saying that the construction works would be completed by 2022.
It is to be noted that the progress in the construction works could have been achieved only 22 percent during the last eight years due to fund complications. The project at a cost of Tk 8,703 crore began in 2011.
As per bridge division information, even the time of construction has been extended, but the cost will remain the same. Within 2020, they are now eyeing to open the first phase of the expressway and by 2022; the total construction work will be completed.
AHMS Aktar, Superintending Engineer of the Support to Dhaka Elevated Expressway PPP Project said, the first phase construction works of the expressway from Airport to Banani has achieved 50 percent progress. This portion will be opened for vehicular movement by September next year.
He informed that they got the financial solution when Ital-Thai, the two organizations became partners of the project. Now they own 51 percent share of the project. Of this, China Shandong International Economic and Technical Company Group Limited have 35 percent and Sinohydro has 14 percent ownership. They have already started to release funds.
The project work starting from the airport will reach Kutubkhali of the Dhaka-Chattogram highway via Kuril, Banani, Mohakhali, Tejgaon, Moghbazar, Kamalapur, Sayedabad and Jatrabari. The main project cost has been estimated at Tk 8940 crore. Of the amount, Italian-Thai Development Public Company Ltd invested Tk 6,444.31 crore and the rest Tk 2413.80 crore will be spent by the government from its own fund as Viability Gap Fund (VGF).
The Executive Committee of the National Economic Council (ECNEC) approved the project in October 2011. The project work was supposed to start in July 2011 to finish in December 2014. During that time, the project cost was estimated at Tk 3216.87 crore. But later, due to some addition and time extension of the project, the revised cost stood at Tk 4,869 crore, and execution time extended to 2020.