Rooppur begins trial power generation in first unit


Published : 01 Nov 2026 10:47 AM

Ishwardi (Pabna) Correspondent

The first unit of the Rooppur Nuclear Power Plant in Ishwardi, Pabna, has begun trial power generation, marking a major step towards supplying electricity to the national grid.

Science and Technology Minister Fakir Mahbub Anam confirmed the development to journalists on Friday afternoon. He said the second phase of the nuclear reaction in the first unit began at around noon and was completed.

On Thursday, the first unit received approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) to begin Stage C, or power start-up activities, following the completion of necessary physical start-up tests.

Project sources said Stage B-1 of the first unit, built with Russian assistance in accordance with International Atomic Energy Agency (IAEA) guidelines, had been completed successfully. Complications involving the final test of the automatic pressure relief valves had also been resolved.

The next phase, Stage B-2, involves preparing the reactor for initial operation and achieving criticality, when a self-sustaining nuclear chain reaction is established. Once power output gradually reaches 300MW, electricity will be supplied to the national grid.

After completing the physical tests under Stage B-2, project authorities submitted a report on the results and progress to BAERA. Following a review, BAERA Chairman M Mahmudul Hasan approved a controlled nuclear fission reaction in the first unit on October 8. The reaction began on October 11.

Nuclear Power Plant Company Bangladesh Limited (NPCBL) Managing Director Dr Md Jahedul Hasan had earlier said the unit would enter Stage C following regulatory approval, paving the way for power generation.

Initially, the unit will operate at around three per cent of its capacity, with output gradually increased to 20-30 per cent. If all tests produce satisfactory results, around 300MW could be supplied to the national grid on a trial basis by the end of December.

Generation will continue to increase gradually after grid connection. Trial operations will continue for some time even after the unit reaches full capacity, before commercial production begins. The process is expected to take seven to eight months.

Once connected to the national grid, the first unit will make Bangladesh the world's 33rd country to generate nuclear power, adding a new source of electricity to the country's energy mix.

The plant has two units, each with a generation capacity of 1,200MW, giving it a combined capacity of 2,400MW. Both units are expected to help reduce load-shedding and save foreign currency currently spent on fuel imports. Nuclear power is also expected to cost less than electricity generated from oil and coal.

Russia's state-owned nuclear corporation Rosatom is assisting in implementing the project, while its subsidiary Atomstroyexport is the contractor.

Meanwhile, Rosatom said in a press release on Thursday that Russia had begun supplying nuclear fuel for the second unit's VVER-1200 reactor. The fuel is expected to reach Rooppur by December, with loading scheduled to begin in June next year.

The Tk 1,13,092 crore project is being implemented with Russian assistance, with Tk 91,040 crore provided as a loan, covering 90 per cent of the total cost. The remainder will be borne by the Bangladesh government. #EK